Classroom Addition

Completed for the week ending July 12, 2019:

  • Precast Wall Panels began being set.
  • Interior renovation and additions continued with mechanical, electrical demolition. Casework relocation and ceiling removal in the second floor space where the addition will tie-into the existing building.

 

Planned for the week ending July 19, 2019:

  • Precast walls to finish being set.
  • Interior demolition to be completed in the existing building.
  • Interior remodel work to continue in the existing building.
  • Parking lot and site work to begin this week in the front of the building. School use entrance will be moved to the east side entrance.

 

Fitness Addition

Completed for the week ending July 12, 2019:

  • Interior renovation and connection work continued.
  • New windows in Kindergarten room were cut in and being prepped for new window install.

 

Planned for the week ending July 19, 2019:

  • Precast wall panels to be set.
  • Interior renovation work to continue.