Classroom Addition

Completed for the week ending May 31, 2019:

  • Gas line relocation was completed by CenterPoint Energy.
  • The Tradesmen Construction began the building demolition of the existing shop space.
  • Soil correction began along with footing and foundation removal of the existing building.
  • Weekly construction meeting took place on Thursday.
  • Technology coordination discussion took place after the meeting Furniture samples were reviewed and discussed.

Planned for the week ending June 7, 2019:

  • Existing building demolition of footings and foundations to be completed.
  • Soil corrections to continue
  • Braun Intertec to provide guidance on scope and depths of soil corrections Construction meeting to take place on Thursday.

 

Fitness Addition

Completed for the week ending May 31, 2019:

  • Tree was cut down previously and ready for excavation to begin.

Planned for the week ending June 7, 2019:

No work planned on the Fitness Addition this week.  Excavation planned to begin after soil corrections are completed on the Classroom Addition