Classroom Addition
Completed for the week ending August 16, 2019:
- Underground plumbing work continues.
- Underground electrical work continues.
- Interior renovation work to continued with sheetrocking, taping and sanding.
- Existing room casework relocation took place.
- Exterior site work with removals and underground electrical underway.
- Parking lot light pole base installation took place.
Planned for the week ending August 23, 2019:
- Roofing to begin.
- Interior masonry walls to begin.
- Underground plumbing work to continue.
- Underground electrical to be wrapped up.
- Interior renovation work to be completed.
- Sitework prep to continue with asphalt removal and site prep to take place.
Fitness Addition
Completed for the week ending August 16, 2019:
- Additional door opening cut in
- Bar joists in existing building for increased show load have been installed New roof drains have been cut into existing roof and roofed in
- New roof parapet wall framing completed, and roofing has begun.
- Interior renovation work continued with wall infills, wall framing and mechanical modifications.
Planned for the week ending August 23, 2019:
- New roof work to be completed.
- Roof drain piping to continue through the new addition.
- Interior modifications to be completed in existing spaces.