Classroom Addition

Completed for the week ending September 13, 2019:

  • Roofing continued as weather permitted.
  • Masonry firewall work completed.
  • Interior masonry walls underway.
  • Second floor plumbing and electrical penetrations taking place.
  • Underground plumbing work nearing completion.

 

Planned for the week ending September 20, 2019:

  • Roofing to continue as weather allows
  • Interior masonry walls to continue
  • Second floor plumbing rough-ins to continue
  • Additional site concrete to be poured, weather permitting
  • Asphalt paving schedule being reviewed with the weather delays

 

Fitness Addition

Completed for the week ending September 13, 2019:

  • Concrete floor slab poured.

 

Planned for the week ending September 20, 2019:

  • Window install to begin
  • Exterior concrete to be redone where imperfections exist from original placement.