Classroom Addition

Completed for the week ending September 20, 2019:

  • Roofing continued as weather permitted.
  • Interior masonry walls continued
  • Second floor plumbing and electrical rough-in work continued.
  • Window frames begin to be set.

 

Planned for the week ending September 27, 2019:

  • Roofing to be completed.
  • Site concrete to be prepped and poured.
  • Interior masonry walls to be completed.
  • Second floor mechanical rough-in work to continue.
  • Existing boiler room modifications to be completed.
  • Window frames continue to be set.
  • Second floor plumbing rough-ins to continue
  • Additional site concrete to be poured, weather permitting
  • Asphalt paving schedule being reviewed with the weather delays, currently planned for the week of 9-30.

Fitness Addition

Completed for the week ending September 20, 2019:

  • Window frame install underway.
  • Metal stud framing has begun.
  • Roof drain piping installed.
  • Hydronic piping rough-in underway.

 

Planned for the week ending September 27, 2019:

  • Metal stud framing to be completed.
  • Mechanical and electrical rough-in work to continue.