Classroom Addition
Completed for the week ending September 27, 2019:
- Roofing completed, flashing install is underway.
- Interior masonry walls continued
- Window frames continue to be set
- Mechanical rough-in work continued
- Sitework prep for concrete aprons, curbs and sidewalk work taking place.
- Existing boiler room modification work continued
Planned for the week ending October 4, 2019:
- Roof flashing installation to continue.
- Site concrete to be prepped and poured.
- Interior masonry walls to continue.
- Second floor concrete topping to be poured.
- Window frames to continue being set.
- Additional site concrete to be poured, weather permitting
Fitness Addition
Completed for the week ending September 27, 2019:
- Window frame install took place.
- Metal stud framing completed.
- Mechanical and Electrical rough-in work continued.
Planned for the week ending October 4, 2019:
- Mechanical and electrical rough-in work to continue.
- Sheetrock installation to begin.