Classroom Addition
Completed for the week ending October 4, 2019:
- Roof flashing installation continued.
- Site concrete areas prepped for new curb and gutter and aprons.
- Interior masonry walls continued in the shop area.
- Second floor concrete topping poured and interior wall layout in process.
- Interior wall framing on second floor has begun.
- Window frames have all been set.
- Existing boiler room modification work continued.
- Precast wall patching taking place.
Planned for the week ending October 11, 2019:
- Roof flashing installation to be completed Site concrete to be poured.
- Interior masonry walls to continue in shop area.
- Second floor wall framing to continue.
- Second floor mechanical and electrical work.
- Temporary poly over window openings to be installed until glass arrives.
- Parking lot paving to take place near the end of the week.
FITNESS ADDITION
Completed for the week ending October 4, 2019:
- Mechanical and Electrical rough-in work completed.
- Roof flashing continued to take place.
Planned for the week ending October 11, 2019:
- Sheetrock installation to begin.
- Temporary poly over all windows to be installed.
- Aluminum entrance doors and frames to be installed.
- Roof flashing to be completed.