Classroom Addition
Completed for the week ending October 11, 2019:
 Roof flashing installation continued and is 99% complete.
 Site concrete areas began being poured.
 Interior masonry walls continued in the shop area.
 Interior wall framing on second floor completed.
 Mechanical and Electrical work on the second floor continues.
 Existing boiler room modification work completed for boiler operation.
 First Floor classroom floor slabs poured.

Planned for the week ending October 18, 2019:
 Temporary heat to be put in place.
 Second floor mechanical and electrical rough-ins to be completed.
 First floor classroom wall framing to begin.
 First floor classroom mechanical and electrical rough-ins to begin.
 Remaining site concrete to be poured.
 Interior masonry walls to continue in shop area.
 Asphalt paving to take place.
 Site grading and seeding to take place.
 Aluminum entrances to begin being placed earlier this week.

Fitness Addition
Completed for the week ending October 11, 2019:.
 Temporary window covering installed.

Planned for the week ending October 18, 2019:
 Temporary heat to be put in place.
 Sheetrocking to begin being installed.
 Sheetrock installation to continue.
 Temporary poly over all windows to be installed.
 Aluminum entrance doors and frames to be installed.
 Roof flashing to be completed.