Classroom Addition
Completed for the week ending October 25, 2019:
- Temporary heat in place for sheetrock taping to begin.
- Second floor gyp board install began at the end of the week.
- Second floor mechanical and electrical rough-ins completed.
- First floor classroom wall framing continued
- First floor classroom mechanical and electrical rough-ins underway.
- Interior masonry walls continued in shop area.
- Aluminum window sealants began.
Planned for the week ending November 1, 2019:
- Interior masonry walls to continue and be near completion in shop area.
- Aluminum entrances to begin being placed earlier this week.
- Second floor glazing to begin installation.
- Remaining site concrete to be poured.
- Site grading and seeding to take place.
Fitness Addition
Completed for the week ending October 25, 2019:
- Temporary heat put in place.
- Sheetrocking installation took place.
- Sprinkler system rough-ins underway.
- Aluminum Entrance Doors installed.
Planned for the week ending November 1, 2019:
- Sheetrock taping to begin
- Sprinkler system rough-ins to be completed.