Classroom Addition

Completed for the week ending June 28, 2019:

  • Interior Footings were being poured.
  • Foundation walls poured and backfilled.
  • Interior remodel work began with onsite mobilization.

 

Planned for the week ending July 5, 2019:

  • Foundation walls to be wrapped up
  • Interior remodel work to begin

 

Fitness Addition

Completed for the week ending June 28, 2019:

  • Foundation excavation took place.
  • Foundation forming is underway.

Planned for the week ending July 5, 2019:

  • Interior renovation for the Fitness Addition tie in to take place.
  • Footings to be poured and foundation work to begin.

Fitness Addition footing excavation completed

Footings and Foundation Walls continue and are backfilled in many areas

FOUNDATION WALLS POURED AND BACKFILLING PROGRESSING