Classroom Addition
Completed for the week ending September 13, 2019:
- Roofing continued as weather permitted.
- Masonry firewall work completed.
- Interior masonry walls underway.
- Second floor plumbing and electrical penetrations taking place.
- Underground plumbing work nearing completion.
Planned for the week ending September 20, 2019:
- Roofing to continue as weather allows
- Interior masonry walls to continue
- Second floor plumbing rough-ins to continue
- Additional site concrete to be poured, weather permitting
- Asphalt paving schedule being reviewed with the weather delays
Fitness Addition
Completed for the week ending September 13, 2019:
- Concrete floor slab poured.
Planned for the week ending September 20, 2019:
- Window install to begin
- Exterior concrete to be redone where imperfections exist from original placement.