Completed for the week ending September 20, 2019:
- Roofing continued as weather permitted.
- Interior masonry walls continued
- Second floor plumbing and electrical rough-in work continued.
- Window frames begin to be set.
Planned for the week ending September 27, 2019:
- Roofing to be completed.
- Site concrete to be prepped and poured.
- Interior masonry walls to be completed.
- Second floor mechanical rough-in work to continue.
- Existing boiler room modifications to be completed.
- Window frames continue to be set.
- Second floor plumbing rough-ins to continue
- Additional site concrete to be poured, weather permitting
- Asphalt paving schedule being reviewed with the weather delays, currently planned for the week of 9-30.
Fitness Addition
Completed for the week ending September 20, 2019:
- Window frame install underway.
- Metal stud framing has begun.
- Roof drain piping installed.
- Hydronic piping rough-in underway.
Planned for the week ending September 27, 2019:
- Metal stud framing to be completed.
- Mechanical and electrical rough-in work to continue.