Classroom Addition
Completed for the week ending October 11, 2019:
Roof flashing installation continued and is 99% complete.
Site concrete areas began being poured.
Interior masonry walls continued in the shop area.
Interior wall framing on second floor completed.
Mechanical and Electrical work on the second floor continues.
Existing boiler room modification work completed for boiler operation.
First Floor classroom floor slabs poured.
Planned for the week ending October 18, 2019:
Temporary heat to be put in place.
Second floor mechanical and electrical rough-ins to be completed.
First floor classroom wall framing to begin.
First floor classroom mechanical and electrical rough-ins to begin.
Remaining site concrete to be poured.
Interior masonry walls to continue in shop area.
Asphalt paving to take place.
Site grading and seeding to take place.
Aluminum entrances to begin being placed earlier this week.
Fitness Addition
Completed for the week ending October 11, 2019:.
Temporary window covering installed.
Planned for the week ending October 18, 2019:
Temporary heat to be put in place.
Sheetrocking to begin being installed.
Sheetrock installation to continue.
Temporary poly over all windows to be installed.
Aluminum entrance doors and frames to be installed.
Roof flashing to be completed.