Classroom Addition

Completed for the week ending October 25, 2019:

  • Temporary heat in place for sheetrock taping to begin.
  • Second floor gyp board install began at the end of the week.
  • Second floor mechanical and electrical rough-ins completed.
  • First floor classroom wall framing continued
  • First floor classroom mechanical and electrical rough-ins underway.
  • Interior masonry walls continued in shop area.
  • Aluminum window sealants began.

 

 

Planned for the week ending November 1, 2019:

  • Interior masonry walls to continue and be near completion in shop area.
  • Aluminum entrances to begin being placed earlier this week.
  • Second floor glazing to begin installation.
  • Remaining site concrete to be poured.
  • Site grading and seeding to take place.

 

Fitness Addition

Completed for the week ending October 25, 2019:

  • Temporary heat put in place.
  • Sheetrocking installation took place.
  • Sprinkler system rough-ins underway.
  • Aluminum Entrance Doors installed.

 

Planned for the week ending November 1, 2019:

  • Sheetrock taping to begin
  • Sprinkler system rough-ins to be completed.