Classroom Addition

Completed for the week ending November 1, 2019:

  • Second floor gyp board install continued.
  • Second floor mechanical and electrical rough-ins completed.
  • Second floor window glazing took place.
  • First floor classroom wall framing completed.
  • First floor classroom mechanical and electrical rough-ins continue Interior masonry walls continued in shop area.
  • Aluminum window sealants underway.
  • Interior masonry walls to continue and be near completion in shop area.

 

Planned for the week ending November 8, 2019:

  • Gyp board taping to begin on the second floor.
  • Aluminum window sealants to continue to be installed.
  • Mechanical and Electrical rough-ins continue on the first floor.
  • Temporary enclosures to continue to be installed to allow temp heating. Interior masonry walls to continue and be near completion in shop area.
  • Shop area storage room ceiling structure to be installed.

 

Fitness Addition

Completed for the week ending November 1, 2019:

  • Temporary heat put in place and running.
  • Sprinkler system rough-ins completed.
  • Electrical panel install took place.

 

Planned for the week ending November 8, 2019:

  • Sheetrock taping to begin