Classroom Addition

Completed for the week ending June 7, 2019:

  • Existing building demolition of footings and foundations was completed.
  • Soil corrections continued
  • Braun Intertec to provide guidance on scope and depths of soil corrections Building Pad Sand Cushion hauled in and placed.
  • Additional Furniture samples were reviewed and discussed.

 

Planned for the week ending June 14, 2019:

  • Footings to be formed and poured.
  • Interior Mechanical and Electrical work to begin routing for tie into building additions.
  • Potential Parking Lot work to begin in conjunction with excavation activities.
  • Construction meeting to take place on Thursday.

 

Fitness Addition

Completed for the week ending June 7, 2019:

  • No work planned on the Fitness Addition this week

 

Planned for the week ending June 14, 2019:

  • Excavation potentially to begin depending on Classroom Addition work progress.