Classroom Addition
Completed for the week ending July 12, 2019:
- Precast Wall Panels finished being set with the exception of the south end to allow crane access.
- Interior demolition was completed.
- Interior remodel work continued.
- Structural Steel began being set.
- Masonry piers were installed.
- Roof Top Mechanical Units have been delivered to the site.
Planned for the week ending July 19, 2019: § Precast roof structure to begin being set.
- Interior masonry piers to continue.
- Interior renovation work to continue framing over existing windows.
- Parking lot and site work to begin this week in the front of the building. School use entrance will be moved to the North entrance/Multi-Purpose Entrance.
Fitness Addition
Completed for the week ending July 12, 2019:
- Precast wall panels were set.
- Interior structural piers were poured.
- Interior renovation work continued with Mechanical demolition.
Planned for the week ending July 19, 2019:
- Roof drain modifications to take place to tie into the new storm sewer lines.
- Interior renovation work to continue.