Completed for the week ending July 26, 2019:
- Precast Wall Panels base grouting was completed
- Precast Wall Panel caulking is underway
- Interior demolition work continued with the framing over the existing windows
- Structural Steel setting has been completed
Planned for the week ending August 2, 2019:
- Precast roof structure to begin being set.
- Interior masonry to potentially begin at the end of the week
- Interior renovation work to continue with window work and new beam for the connection opening
Fitness Addition
Completed for the week ending July 26, 2019:
- Precast walls were backfilled
- Interior demolition continued at the connection from the existing to the fitness addition.
Planned for the week ending August 2, 2019:
- Roof drain modifications to begin being routed for tie in to the new storm sewer lines.