Classroom Addition
Completed for the week ending August 2, 2019:
- Precast roof structure and second floor precast plank were set.
- Precast wall panels remaining to be set were completed.
- Interior renovation work continued with window work and new connection work from existing building.
Planned for the week ending August 9, 2019:
- Precast roof structure to begin being set.
- Interior masonry walls to begin.
- Underground plumbing work to begin.
- Interior renovation work to continue with window work and new beam for the connection opening
Fitness Addition
Completed for the week ending August 2, 2019:
- Interior renovation work for the new connection continued.
Planned for the week ending August 9, 2019:
- Roof drain modifications to begin being routed for tie in to the new storm sewer lines.
- Interior renovation work to continue with infills at old windows and new connection details.