Hancock Public School Classroom/Fitness Addition Weekly Update August 19th

  Classroom Addition Completed for the week ending August 16, 2019: Underground plumbing work continues. Underground electrical work continues. Interior renovation work to continued with sheetrocking, taping and sanding. Existing room casework relocation took place. Exterior site work with removals and underground electrical underway. Parking lot light pole base installation took place.                                Planned for…