Classroom Addition

Completed for the week ending August 16, 2019:

  • Underground plumbing work continues.
  • Underground electrical work continues.
  • Interior renovation work to continued with sheetrocking, taping and sanding.
  • Existing room casework relocation took place.
  • Exterior site work with removals and underground electrical underway.
  • Parking lot light pole base installation took place.

                              

Planned for the week ending August 23, 2019:

  • Roofing to begin.
  • Interior masonry walls to begin.
  • Underground plumbing work to continue.
  • Underground electrical to be wrapped up.
  • Interior renovation work to be completed.
  • Sitework prep to continue with asphalt removal and site prep to take place.

 

Fitness Addition

Completed for the week ending August 16, 2019:

  • Additional door opening cut in
  • Bar joists in existing building for increased show load have been installed New roof drains have been cut into existing roof and roofed in
  • New roof parapet wall framing completed, and roofing has begun.
  • Interior renovation work continued with wall infills, wall framing and mechanical modifications.

 

Planned for the week ending August 23, 2019:

  • New roof work to be completed.
  • Roof drain piping to continue through the new addition.
  • Interior modifications to be completed in existing spaces.