Classroom Addition
Completed for the week ending September 6, August 30, 2019:
- Underground plumbing work continues.
- Sitework storm water piping complete.
- Existing classroom addition reroofing underway.
- Masonry firewall installation is taking place.
Planned for the week ending September 13, 2019:
- Roofing to continue.
- Masonry firewall to be completed.
- Interior masonry walls to begin.
- Underground plumbing work to be completed.
- Second floor plumbing rough-ins to begin.
- Additional site concrete to be poured.
- Asphalt paving scheduled for Friday.
Fitness Addition
Completed for the week ending September 6, 2019:
- Underground storm water piping completed on the exterior.
Planned for the week ending September 13, 2019:
- Concrete floor slab to be poured.
Exterior concrete to be redone where imperfections exist from original placement.