Classroom Addition

Completed for the week ending September 6, August 30, 2019:

  • Underground plumbing work continues.
  • Sitework storm water piping complete.
  • Existing classroom addition reroofing underway.
  • Masonry firewall installation is taking place.

 

Planned for the week ending September 13, 2019:

  • Roofing to continue.
  • Masonry firewall to be completed.
  • Interior masonry walls to begin.
  • Underground plumbing work to be completed.
  • Second floor plumbing rough-ins to begin.
  • Additional site concrete to be poured.
  • Asphalt paving scheduled for Friday.

 

 

Fitness Addition

Completed for the week ending September 6, 2019:

  • Underground storm water piping completed on the exterior.

 

Planned for the week ending September 13, 2019:

  • Concrete floor slab to be poured.

Exterior concrete to be redone where imperfections exist from original placement.