Classroom Addition

Completed for the week ending September 27, 2019:

  • Roofing completed, flashing install is underway.
  • Interior masonry walls continued
  • Window frames continue to be set
  • Mechanical rough-in work continued
  • Sitework prep for concrete aprons, curbs and sidewalk work taking place.
  • Existing boiler room modification work continued

 

Planned for the week ending October 4, 2019:

  • Roof flashing installation to continue.
  • Site concrete to be prepped and poured.
  • Interior masonry walls to continue.
  • Second floor concrete topping to be poured.
  • Window frames to continue being set.
  • Additional site concrete to be poured, weather permitting

 

Fitness Addition

Completed for the week ending September 27, 2019:

  • Window frame install took place.
  • Metal stud framing completed.
  • Mechanical and Electrical rough-in work continued.

 

Planned for the week ending October 4, 2019:

  • Mechanical and electrical rough-in work to continue.
  • Sheetrock installation to begin.