Classroom Addition
Completed for the week ending October 18, 2019:
- Asphalt paving took place.
- Interior masonry walls continued in the shop area Second floor mechanical and electrical rough-ins continued.
- First floor classroom wall framing underway.
Planned for the week ending October 25, 2019:
- Temporary heat to be put in place.
- Second floor gyp board install to begin at the end of the week Second floor mechanical and electrical rough-ins to be completed.
- First floor classroom wall framing to continue
- First floor classroom mechanical and electrical rough-ins to begin.
- Remaining site concrete to be poured.
- Interior masonry walls to continue in shop area.
- Site grading and seeding to take place.
- Aluminum entrances to begin being placed earlier this week.
Fitness Addition
Completed for the week ending October 18, 2019:.
- Temporary heat put in place.
- Sheetrock staging took place and ready to begin install.
- Hydronic connections in existing building took place over MEA
Planned for the week ending October 25, 2019:
- Temporary heat to be put in place.
- Sheetrocking to begin being installed.
- Sheetrock installation to continue.
- Aluminum entrance doors and frames to be installed.
- Sprinkler system rough-ins to take place.