Classroom Addition

Completed for the week ending October 18, 2019:

  • Asphalt paving took place.
  • Interior masonry walls continued in the shop area Second floor mechanical and electrical rough-ins continued.
  • First floor classroom wall framing underway.

 

Planned for the week ending October 25, 2019:

  • Temporary heat to be put in place.
  • Second floor gyp board install to begin at the end of the week Second floor mechanical and electrical rough-ins to be completed.
  • First floor classroom wall framing to continue
  • First floor classroom mechanical and electrical rough-ins to begin.
  • Remaining site concrete to be poured.
  • Interior masonry walls to continue in shop area.
  • Site grading and seeding to take place.
  • Aluminum entrances to begin being placed earlier this week.

 

Fitness Addition

Completed for the week ending October 18, 2019:.

  • Temporary heat put in place.
  • Sheetrock staging took place and ready to begin install.
  • Hydronic connections in existing building took place over MEA

 

Planned for the week ending October 25, 2019:

  • Temporary heat to be put in place.
  • Sheetrocking to begin being installed.
  • Sheetrock installation to continue.
  • Aluminum entrance doors and frames to be installed.
  • Sprinkler system rough-ins to take place.