Classroom Addition
Completed for the week ending November 1, 2019:
- Second floor gyp board install continued.
- Second floor mechanical and electrical rough-ins completed.
- Second floor window glazing took place.
- First floor classroom wall framing completed.
- First floor classroom mechanical and electrical rough-ins continue Interior masonry walls continued in shop area.
- Aluminum window sealants underway.
- Interior masonry walls to continue and be near completion in shop area.
Planned for the week ending November 8, 2019:
- Gyp board taping to begin on the second floor.
- Aluminum window sealants to continue to be installed.
- Mechanical and Electrical rough-ins continue on the first floor.
- Temporary enclosures to continue to be installed to allow temp heating. Interior masonry walls to continue and be near completion in shop area.
- Shop area storage room ceiling structure to be installed.
Fitness Addition
Completed for the week ending November 1, 2019:
- Temporary heat put in place and running.
- Sprinkler system rough-ins completed.
- Electrical panel install took place.
Planned for the week ending November 8, 2019:
- Sheetrock taping to begin