Classroom Addition Completed for the week ending October 18, 2019: Asphalt paving took place. Interior masonry walls continued in the shop area Second floor mechanical and electrical rough-ins continued. First floor classroom wall framing underway. Planned for the week ending October 25, 2019: Temporary heat to be put in place. Second floor gyp board…
Read MoreLast spring the Hancock Business Professionals of America received one of the highest honors possible for the club. At the national convention they were named the CARES Award winner. The CARES award is a national honor for outstanding Community Service work and stands for (Cares is not an acronym) Participation in this program means that…
Read MoreClassroom Addition Completed for the week ending October 11, 2019: Roof flashing installation continued and is 99% complete. Site concrete areas began being poured. Interior masonry walls continued in the shop area. Interior wall framing on second floor completed. Mechanical and Electrical work on the second floor continues. Existing…
Read MoreHancock Public School Athletes of the Month Throughout the school year, Hancock coaches of each activity will select 1 student athlete to acknowledge not only students’ athletic achievements, but also the sort of exceptional character traits — perseverance, integrity, selflessness and sportsmanship — that make them leaders on the field, in the classroom and throughout…
Read MoreHANCOCK PUBLIC SCHOOL STUDENT OF THE MONTH The administration and faculty of Hancock Public School are pleased to announce the Students of the Month for October. These students are chosen because of their exemplary citizenship, positive attitude, and dedication to academic excellence. October Junior High Student of the Month Kaylee Wink October…
Read MoreClassroom Addition Completed for the week ending October 4, 2019: Roof flashing installation continued. Site concrete areas prepped for new curb and gutter and aprons. Interior masonry walls continued in the shop area. Second floor concrete topping poured and interior wall layout in process. Interior wall framing on second floor has begun. Window frames have…
Read MoreClassroom Addition Completed for the week ending September 27, 2019: Roofing completed, flashing install is underway. Interior masonry walls continued Window frames continue to be set Mechanical rough-in work continued Sitework prep for concrete aprons, curbs and sidewalk work taking place. Existing boiler room modification work continued Planned for the week ending October 4,…
Read MoreHomecoming 2019 Congratulations to our 2019 Homecoming King Tyler Timmerman and Queen Bailey DeSmith! Royalty Candidates Seniors Miranda Chamberlain & Tyler Timmerman Juniors …
Read MoreClassroom Addition Completed for the week ending September 20, 2019: Roofing continued as weather permitted. Interior masonry walls continued Second floor plumbing and electrical rough-in work continued. Window frames begin to be set. Planned for the week ending September 27, 2019: Roofing to be completed. Site concrete to be prepped and poured. Interior masonry…
Read MoreHomecoming Week: September 23rd-27th. Monday, September 23rd: Pajama Day Coronation @ 7:00 pm. HCC Soup and Pie Supper Monday, September 23rd, in the Cafeteria from 5:00-6:30 pm. JV football versus Verndale at home. Game time is 4:30 pm. Tuesday, September 24th: Beach/Hawaiian Day B-squad and varsity volleyball at HLA. Game time is 6:00 pm. Junior…
Read More