Classroom Addition

Completed for the week ending July 12, 2019:

  • Precast Wall Panels finished being set with the exception of the south end to allow crane access.
  • Interior demolition was completed.
  • Interior remodel work continued.
  • Structural Steel began being set.
  • Masonry piers were installed.
  • Roof Top Mechanical Units have been delivered to the site.

Planned for the week ending July 19, 2019: § Precast roof structure to begin being set.

  • Interior masonry piers to continue.
  • Interior renovation work to continue framing over existing windows.
  • Parking lot and site work to begin this week in the front of the building. School use entrance will be moved to the North entrance/Multi-Purpose Entrance.

Fitness Addition

Completed for the week ending July 12, 2019:

  • Precast wall panels were set.
  • Interior structural piers were poured.
  • Interior renovation work continued with Mechanical demolition.

Planned for the week ending July 19, 2019:

  • Roof drain modifications to take place to tie into the new storm sewer lines.
  • Interior renovation work to continue.