Classroom Addition

Completed for the week ending July 26, 2019:

  • Precast Wall Panels base grouting was completed
  • Precast Wall Panel caulking is underway
  • Interior demolition work continued with the framing over the existing windows
  • Structural Steel setting has been completed

 

Planned for the week ending August 2, 2019:

  • Precast roof structure to begin being set.
  • Interior masonry to potentially begin at the end of the week
  • Interior renovation work to continue with window work and new beam for the connection opening

 

Fitness Addition

Completed for the week ending July 26, 2019:

  • Precast walls were backfilled
  • Interior demolition continued at the connection from the existing to the fitness addition.

 

Planned for the week ending August 2, 2019:

  • Roof drain modifications to begin being routed for tie in to the new storm sewer lines.
  • Interior renovation work to continue.