Classroom Addition

Completed for the week ending August 2, 2019:

  • Precast roof structure and second floor precast plank were set.
  • Precast wall panels remaining to be set were completed.
  • Interior renovation work continued with window work and new connection work from existing building.

                              

Planned for the week ending August 9, 2019:

  • Precast roof structure to begin being set.
  • Interior masonry walls to begin.
  • Underground plumbing work to begin.
  • Interior renovation work to continue with window work and new beam for the connection opening

 

Fitness Addition

Completed for the week ending August 2, 2019:

  • Interior renovation work for the new connection continued.

 

Planned for the week ending August 9, 2019:

  • Roof drain modifications to begin being routed for tie in to the new storm sewer lines.
  • Interior renovation work to continue with infills at old windows and new connection details.