Classroom Addition Completed for the week ending July 26, 2019: Precast Wall Panels base grouting was completed Precast Wall Panel caulking is underway Interior demolition work continued with the framing over the existing windows Structural Steel setting has been completed Planned for the week ending August 2, 2019: Precast roof structure to begin being…
Read MoreClassroom Addition Completed for the week ending July 12, 2019: Precast Wall Panels finished being set with the exception of the south end to allow crane access. Interior demolition was completed. Interior remodel work continued. Structural Steel began being set. Masonry piers were installed. Roof Top Mechanical Units have been delivered to the site. Planned…
Read MoreClassroom Addition Completed for the week ending July 12, 2019: Precast Wall Panels began being set. Interior renovation and additions continued with mechanical, electrical demolition. Casework relocation and ceiling removal in the second floor space where the addition will tie-into the existing building. Planned for the week ending July 19, 2019: Precast walls to…
Read MoreThe Class of 1969 held their 50 year class reunion over the Hancock July 4th celebration. They entered a float in the Hancock parade, took a tour of the school and enjoyed the weekend to reminisce!
Read MoreHancock Public School has been selected by a local farmer as a 2019 America’s Farmers Grow Communities winning nonprofit organization! A $2,500 donation from Grow Communities, sponsored by the Bayer Fund is an honor and that not only positively impacts the school but our community as well. Started in 2010, the America’s Farmers programs, sponsored by…
Read MoreClassroom Addition Completed for the week ending June 28, 2019: Interior Footings were being poured. Foundation walls poured and backfilled. Interior remodel work began with onsite mobilization. Planned for the week ending July 5, 2019: Foundation walls to be wrapped up Interior remodel work to begin Fitness Addition Completed for the week ending…
Read More