Homecoming Week: September 23rd-27th. Monday, September 23rd: Pajama Day Coronation @ 7:00 pm. HCC Soup and Pie Supper Monday, September 23rd, in the Cafeteria from 5:00-6:30 pm. JV football versus Verndale at home. Game time is 4:30 pm. Tuesday, September 24th: Beach/Hawaiian Day B-squad and varsity volleyball at HLA. Game time is 6:00 pm. Junior…
Read MoreClassroom Addition Completed for the week ending September 13, 2019: Roofing continued as weather permitted. Masonry firewall work completed. Interior masonry walls underway. Second floor plumbing and electrical penetrations taking place. Underground plumbing work nearing completion. Planned for the week ending September 20, 2019: Roofing to continue as weather allows Interior masonry walls to…
Read MoreNOTICE OF SALE BY SEALED BID CITY OF HANCOCK, STEVENS COUNTY Property (sold separately): house, detached garage and storage shed located at 820 2nd Street, Hancock, Minnesota. Additional information about the property may be obtained by writing Leuthner & Huether, Ltd., Attn: William J. Leuthner, 109 East 6th Street, Morris, MN 56267, or…
Read MoreClassroom Addition Completed for the week ending September 6, August 30, 2019: Underground plumbing work continues. Sitework storm water piping complete. Existing classroom addition reroofing underway. Masonry firewall installation is taking place. Planned for the week ending September 13, 2019: Roofing to continue. Masonry firewall to be completed. Interior masonry walls to begin. Underground…
Read MorePlease note that this bus route schedule is similar to last year and is still subject to change. All bus routes will begin daily at approximately 6:45 and end at the school at approx. 8:10. PLEASE allow a 10 minute window and have your child(ren) ready to board the bus. It is…
Read MoreClassroom Addition Completed for the week ending August 16, 2019: Underground plumbing work continues. Underground electrical work continues. Interior renovation work to continued with sheetrocking, taping and sanding. Existing room casework relocation took place. Exterior site work with removals and underground electrical underway. Parking lot light pole base installation took place. Planned for…
Read MoreClassroom Addition Completed for the week ending August 9, 2019: Underground plumbing work underway. Underground electrical work underway. Interior renovation work to continued with structural reinforcement and window infills. Exterior site grading and topsoil placement is underway. Planned for the week ending August 16, 2019: Roofing to begin. Mechanical roof drain piping from existing…
Read MoreClassroom Addition Completed for the week ending August 2, 2019: Precast roof structure and second floor precast plank were set. Precast wall panels remaining to be set were completed. Interior renovation work continued with window work and new connection work from existing building. Planned for the week ending August 9, 2019: Precast roof structure…
Read MoreClassroom Addition Completed for the week ending July 26, 2019: Precast Wall Panels base grouting was completed Precast Wall Panel caulking is underway Interior demolition work continued with the framing over the existing windows Structural Steel setting has been completed Planned for the week ending August 2, 2019: Precast roof structure to begin being…
Read MoreClassroom Addition Completed for the week ending July 12, 2019: Precast Wall Panels finished being set with the exception of the south end to allow crane access. Interior demolition was completed. Interior remodel work continued. Structural Steel began being set. Masonry piers were installed. Roof Top Mechanical Units have been delivered to the site. Planned…