Hancock Public School Classroom/Fitness Addition Weekly Update 9-15-19

Classroom Addition Completed for the week ending September 13, 2019: Roofing continued as weather permitted. Masonry firewall work completed. Interior masonry walls underway. Second floor plumbing and electrical penetrations taking place. Underground plumbing work nearing completion.   Planned for the week ending September 20, 2019: Roofing to continue as weather allows Interior masonry walls to…

Read More

Notice of Sale by Sealed Bid

NOTICE OF SALE BY SEALED BID CITY OF HANCOCK, STEVENS COUNTY   Property (sold separately):  house, detached garage and storage shed located at 820 2nd Street, Hancock, Minnesota.   Additional information about the property may be obtained by writing Leuthner & Huether, Ltd., Attn:  William J. Leuthner, 109 East 6th Street, Morris, MN 56267, or…

Read More

Hancock Public School Classroom/Fitness Addition Weekly Update 9-9-19

Classroom Addition Completed for the week ending September 6, August 30, 2019: Underground plumbing work continues. Sitework storm water piping complete. Existing classroom addition reroofing underway. Masonry firewall installation is taking place.   Planned for the week ending September 13, 2019: Roofing to continue. Masonry firewall to be completed. Interior masonry walls to begin. Underground…

Read More

Hancock Public School Classroom/Fitness Addition Weekly Update August 19th

  Classroom Addition Completed for the week ending August 16, 2019: Underground plumbing work continues. Underground electrical work continues. Interior renovation work to continued with sheetrocking, taping and sanding. Existing room casework relocation took place. Exterior site work with removals and underground electrical underway. Parking lot light pole base installation took place.                                Planned for…

Read More

Hancock Public School Classroom/Fitness Addition Weekly Update Aug 12th

Classroom Addition Completed for the week ending August 9, 2019: Underground plumbing work underway. Underground electrical work underway. Interior renovation work to continued with structural reinforcement and window infills. Exterior site grading and topsoil placement is underway.                                Planned for the week ending August 16, 2019: Roofing to begin. Mechanical roof drain piping from existing…

Read More

Hancock Public School Classroom/Fitness Addition Weekly Update Aug 2nd

Classroom Addition Completed for the week ending August 2, 2019: Precast roof structure and second floor precast plank were set. Precast wall panels remaining to be set were completed. Interior renovation work continued with window work and new connection work from existing building.                                Planned for the week ending August 9, 2019: Precast roof structure…