Hancock Public School Classroom/Fitness Addition Weekly Update Aug 12th

Classroom Addition Completed for the week ending August 9, 2019: Underground plumbing work underway. Underground electrical work underway. Interior renovation work to continued with structural reinforcement and window infills. Exterior site grading and topsoil placement is underway.                                Planned for the week ending August 16, 2019: Roofing to begin. Mechanical roof drain piping from existing…

Read More

Hancock Public School Classroom/Fitness Addition Weekly Update Aug 2nd

Classroom Addition Completed for the week ending August 2, 2019: Precast roof structure and second floor precast plank were set. Precast wall panels remaining to be set were completed. Interior renovation work continued with window work and new connection work from existing building.                                Planned for the week ending August 9, 2019: Precast roof structure…