Classroom Addition Completed for the week ending July 12, 2019: Precast Wall Panels began being set. Interior renovation and additions continued with mechanical, electrical demolition. Casework relocation and ceiling removal in the second floor space where the addition will tie-into the existing building. Planned for the week ending July 19, 2019: Precast walls to…
Read MoreThe Class of 1969 held their 50 year class reunion over the Hancock July 4th celebration. They entered a float in the Hancock parade, took a tour of the school and enjoyed the weekend to reminisce!
Read MoreHancock Public School has been selected by a local farmer as a 2019 America’s Farmers Grow Communities winning nonprofit organization! A $2,500 donation from Grow Communities, sponsored by the Bayer Fund is an honor and that not only positively impacts the school but our community as well. Started in 2010, the America’s Farmers programs, sponsored by…
Read MoreClassroom Addition Completed for the week ending June 28, 2019: Interior Footings were being poured. Foundation walls poured and backfilled. Interior remodel work began with onsite mobilization. Planned for the week ending July 5, 2019: Foundation walls to be wrapped up Interior remodel work to begin Fitness Addition Completed for the week ending…
Read MoreClassroom Addition Completed for the week ending June 14, 2019: Perimeter footings were completed. Foundation walls formed and poured. Interior renovation work coordination to take place in preparation for work to begin. Planned for the week ending June 21, 2019: Foundation walls to begin being formed and poured. Interior remodel work coordination to continue. …
Read MoreClassroom Addition Completed for the week ending June 7, 2019: Existing building demolition of footings and foundations was completed. Soil corrections continued Braun Intertec to provide guidance on scope and depths of soil corrections Building Pad Sand Cushion hauled in and placed. Additional Furniture samples were reviewed and discussed. Planned for the week ending…
Read MoreClassroom Addition Completed for the week ending May 31, 2019: Gas line relocation was completed by CenterPoint Energy. The Tradesmen Construction began the building demolition of the existing shop space. Soil correction began along with footing and foundation removal of the existing building. Weekly construction meeting took place on Thursday. Technology coordination discussion took place…
Read MoreHancock Public School Athletes of the Month Throughout the school year, Hancock coaches of each activity will select 1 student athlete to acknowledge not only students’ athletic achievements, but also the sort of exceptional character traits — perseverance, integrity, selflessness and sportsmanship — that make them leaders on the field, in the classroom and throughout…
Read MoreHANCOCK PUBLIC SCHOOL STUDENT OF THE MONTH The administration and faculty of Hancock Public School are pleased to announce the Students of the Month for May. These students are chosen because of their exemplary citizenship, positive attitude, and dedication to academic excellence. May Junior High Student of the Month Sean Wilson May…