Classroom Addition Completed for the week ending October 4, 2019: Roof flashing installation continued. Site concrete areas prepped for new curb and gutter and aprons. Interior masonry walls continued in the shop area. Second floor concrete topping poured and interior wall layout in process. Interior wall framing on second floor has begun. Window frames have…
Read MoreClassroom Addition Completed for the week ending September 27, 2019: Roofing completed, flashing install is underway. Interior masonry walls continued Window frames continue to be set Mechanical rough-in work continued Sitework prep for concrete aprons, curbs and sidewalk work taking place. Existing boiler room modification work continued Planned for the week ending October 4,…
Read MoreHomecoming 2019 Congratulations to our 2019 Homecoming King Tyler Timmerman and Queen Bailey DeSmith! Royalty Candidates Seniors Miranda Chamberlain & Tyler Timmerman Juniors …
Read MoreClassroom Addition Completed for the week ending September 20, 2019: Roofing continued as weather permitted. Interior masonry walls continued Second floor plumbing and electrical rough-in work continued. Window frames begin to be set. Planned for the week ending September 27, 2019: Roofing to be completed. Site concrete to be prepped and poured. Interior masonry…
Read MoreHomecoming Week: September 23rd-27th. Monday, September 23rd: Pajama Day Coronation @ 7:00 pm. HCC Soup and Pie Supper Monday, September 23rd, in the Cafeteria from 5:00-6:30 pm. JV football versus Verndale at home. Game time is 4:30 pm. Tuesday, September 24th: Beach/Hawaiian Day B-squad and varsity volleyball at HLA. Game time is 6:00 pm. Junior…
Read MoreClassroom Addition Completed for the week ending September 13, 2019: Roofing continued as weather permitted. Masonry firewall work completed. Interior masonry walls underway. Second floor plumbing and electrical penetrations taking place. Underground plumbing work nearing completion. Planned for the week ending September 20, 2019: Roofing to continue as weather allows Interior masonry walls to…
Read MoreNOTICE OF SALE BY SEALED BID CITY OF HANCOCK, STEVENS COUNTY Property (sold separately): house, detached garage and storage shed located at 820 2nd Street, Hancock, Minnesota. Additional information about the property may be obtained by writing Leuthner & Huether, Ltd., Attn: William J. Leuthner, 109 East 6th Street, Morris, MN 56267, or…
Read MoreClassroom Addition Completed for the week ending September 6, August 30, 2019: Underground plumbing work continues. Sitework storm water piping complete. Existing classroom addition reroofing underway. Masonry firewall installation is taking place. Planned for the week ending September 13, 2019: Roofing to continue. Masonry firewall to be completed. Interior masonry walls to begin. Underground…
Read MorePlease note that this bus route schedule is similar to last year and is still subject to change. All bus routes will begin daily at approximately 6:45 and end at the school at approx. 8:10. PLEASE allow a 10 minute window and have your child(ren) ready to board the bus. It is…
Read MoreClassroom Addition Completed for the week ending August 16, 2019: Underground plumbing work continues. Underground electrical work continues. Interior renovation work to continued with sheetrocking, taping and sanding. Existing room casework relocation took place. Exterior site work with removals and underground electrical underway. Parking lot light pole base installation took place. Planned for…